You are viewing an archived web page, collected at the request of United Nations Educational, Scientific and Cultural Organization (UNESCO) using Archive-It. This page was captured on 19:48:21 Mar 27, 2023, and is part of the UNESCO collection. The information on this web page may be out of date. See All versions of this archived page.
Loading media information hide

Take advantage of the search to browse through the World Heritage Centre information.

i
ii
iii
iv
v
vi
vii
viii
ix
x

Butrint

Albania
Factors affecting the property in 2007*
  • Illegal activities
  • Management systems/ management plan
  • Other Threats:

    a) lack of adequate protection management, and conservation of the site b) Poor state of conservation of the propert

Factors* affecting the property identified in previous reports

a) Looting of the Museum of Butrint in 1997

b) lack of adequate protectionmanagement, and conservation of the site

c) Lack of management mechanisms and tourism pressure

d) Poor state of conservation of the property

e) Insufficient implementation of the recommendations of the joint missions;

International Assistance: requests for the property until 2007
Requests approved: 2 (from 1996-1997)
Total amount approved : 106,000 USD
1997 Butrint (Approved)   100,000 USD
1996 Technical assistance for the restoration of Butrint (Approved)   6,000 USD
Missions to the property until 2007**

1997 UNESCO-WHC/ICOMOS/Butrint Foundation mission; 2001 UNESCO-WHC/ICOMOS mission; 2003 UNESCO-WHC/ICOMOS mission; 2005 UNESCO-WHC/ICOMOS/ICCROM mission.

Conservation issues presented to the World Heritage Committee in 2007

On 31 January 2007 the World Heritage Centre received from the State Party a detailed implementation report on the state of conservation of the World Heritage property and a copy of the updated management plan 2007-2012. The State Party also provided the World Heritage Centre with a map of the new proposed boundaries of the site, the relevant governmental decree on the new boundaries andthe management zone description.

The joint UNESCO-WHC/ICOMOS/ICCROM mission requested by the Committee was sent to Albania from 17 to 21 April 2007. The detailed mission report is available at the following Web address: https://whc.unesco.org/archive/2007.

The mission considered that there is considerable improvement in the management of the property. However the participatory approach recommended for the updating of the management plan has not been taken into account. While emphasising the need to update the Management plan, the mission made a series of specific recommendations with a view to ensuring an effective protection of the site and the sustainability of its development. These specific recommendations included:

a) continue to work on the restitution of looted objects in cooperation with the 1970 Convention and ICOM;

b) complete the studies on flooding and implement recommendations;

c) continue to improve infrastructure and visitor parking;

d) enhance capacity building for rangers;

e) control development around the property;

f) improve interpretation panels and

g) enhance international cooperation.

Decisions adopted by the Committee in 2007
31 COM 7B.92
Butrint (Albania)

The World Heritage Committee,

1.       Having examined Document WHC-07/31.COM/7B.Add,

2.       Recalling Decisions 29 COM 7A.27 and 30 COM 7B.75, adopted respectively at its 29th (Durban, 2005) and 30th (Vilnius, 2006) sessions,

3.       Notes the up-dated report and the document “Management Plan 2007-2012” provided by the State Party and  the results of the joint UNESCO-World Heritage Centre/ICOMOS/ICCROM reactive monitoring mission of April 2007 and requests the Management Plan be completed to include proper plans for implementation;

4.       Acknowledges the considerable efforts by the State Party to contribute to the improvements of the state of conservation of the property and its legal protection;

5.       Endorses the recommendations made by the UNESCO-World Heritage Centre/ICOMOS/ICCROM mission of April 2007 and calls upon the State Party to give appropriate attention to their timely implementation;

6.       Requests the State Party:

a)      to ensure that a draft of the completed management and conservation plan of the area is submitted to the World Heritage Centre for review  together with  an interim report not later than by the end of 2008,

b)      to take all necessary measures to prevent any illegal developments or inappropriate construction and uncontrolled growth within the proposed new boundaries, its buffer zone and the vicinity by closely collaborating with other relevant planning and development agencies.

7.       Also requests the State Party to provide the World Heritage Centre with a detailed implementation report on the issues addressed by the April 2007 joint mission, by 1 February 2009 for examination by its 33rd session in 2009.

31 COM 8B.60
Nomination of natural, mixed and cultural properties to the world heritage list - Butrint

The World Heritage Committee,

1. Having examined Documents WHC-07/31.COM/8B.Add and WHC-07/31.COM/INF.8B1.Add,

2. Approves the Butrint National Park as a buffer zone for Butrint, Albania;

3. Requests the State Party to provide documentation on the formal gazetting of the enlarged National Park.

 

Draft Decision: 31 COM 7B.92

The World Heritage Committee,

1. Having examined Document WHC-07/31.COM/7B.Add,

2. Recalling Decisions 29 COM 7A.27 and 30 COM 7B.75, adopted respectively at its 29th (Durban, 2005) and 30th (Vilnius, 2006) sessions,

3. Notes the up-dated report and the document “Management Plan 2007-2012” provided by the State Party and the results of the joint UNESCO-WHC/ICOMOS/ICCROM reactive monitoring mission of April 2007 and requests the Management Plan be completed to include proper plans for implementation;

4. Acknowledges the considerable efforts by the State Party to contribute to the improvements of the state of conservation of the property and its legal protection;

5. Endorses the recommendations made by the UNESCO-WHC/ICOMOS/ICCROM mission of April 2007 and calls upon the State Party to give appropriate attention to their timely implementation;

6. Requests the State Party:

a) to ensure that a draft of the completed management and conservation plan of the area is submitted to the World Heritage Centre for review together with an interim report not later than by the end of 2008,

b) to take all necessary measures to prevent any illegal developments or inappropriate construction and uncontrolled growth within the proposed new boundaries, its buffer zone and the vicinity by closely collaborating with other relevant planning and development agencies.

7. Also requests the State Party to provide the World Heritage Centre with a detailed implementation report on the issues addressed by the April 2007 joint mission, by 1 February 2009 for examination by its 33rd session in 2009.

Report year: 2007
Albania
Date of Inscription: 1992
Category: Cultural
Criteria: (iii)
Danger List (dates): 1997-2005
Documents examined by the Committee
arrow_circle_right 31COM (2007)
Exports

* : The threats indicated are listed in alphabetical order; their order does not constitute a classification according to the importance of their impact on the property.
Furthermore, they are presented irrespective of the type of threat faced by the property, i.e. with specific and proven imminent danger (“ascertained danger”) or with threats which could have deleterious effects on the property’s Outstanding Universal Value (“potential danger”).

** : All mission reports are not always available electronically.